Scheduled Maintenance runs all maintenance tasks regardless of which are selected

When configuring scheduled maintenance, regardless of which of the four tasks are selected to run at the scheduled time, all four tasks will run.

We have evaluated this issue as a potential defect and we have determined it will not be addressed in the software in its current state.  In this case, the risks and challenges outweigh the potential benefit of resolving this issue.

We wish we could address each and every issue that we come across, but there are occasions when addressing certain issues would add risk to causing a bigger problem or would put other prioritized initiatives at risk. 

We strive to select the most impactful changes and issues to address with each release to accelerate the rate at which we deliver new features while sustaining the highest level of quality for our customers.

Steps to Duplicate

1.  Open the Blackbaud Management Console.
2.  Select Maintenance under the desired database you wish to schedule maintenance for.
3.  On the "Welcome to the Schedule Maintenance Wizard" screen, click Next.
4.  On the "Adjust Maintenance Schedule" screen, check the box marked "Enabled" and then set your desired Frequency.  Then click Next.
5.  Select one or more maintenance tasks, then click Next.
6.  Click Next, and then Finish.

Task will be scheduled for all four tasks to run, regardless of which were selected.

Environment

 SQL Server 2008 Express;SQL Server 2008;SQL Server 2008 R2 Express;SQL Server 2008 R2;SQL Server 2012 Express;SQL Server 2012;SQL Server 2014 Express;SQL Server 2014
 Raiser's Edge