If you make changes to the Special Day Template, this will NOT automatically update the days where the Special Day Template was already applied. Instead, you will need to re-apply it to the day(s) where the original unedited Template was used. To do this:
  1. Navigate to onRecord > Procedures > Schedule
  2. Click Master Schedule
  3. Click Edit for the day you need to re-apply the Special Day Template
  4. Click Use Special Day template and select the edited Template
  5. Click Save & Exit
  6. Repeat for any other days that particular Template was used for
Note: When a Special Day Template is used it will overwrite anything that is canceled through onRecord > Procedures > Schedule > Section Schedule.