Opportunity Associated Revenue datalist is over counting line items on Pledges

Users have found that the Opportunity Associated Revenue datalist is over counting line items on Pledges. 

This behavior occurs if an opportunity is added and the designation is changed on a 'Posted' pledge record. 
We're currently evaluating this issue for a fix in a future release.
 

Steps to Duplicate

Prerequisite: 
1. Go to a constituents record.  
2. Add a Pledge to any designation. (For example,  $1,000,000.00) 
3. Do not apply the Pledge to an Opportunity. 
4. Set the Pledge to "Not Posted". 
5. Click Save. 
6. Run a Post process to Post the Pledge.

Steps to Duplicate: 
1. Navigate to the Posted Pledge record. 
2. Edit the Posted Pledge. 
3. Add the Pledge to an Opportunity. 
4. Change the Designation on the Pledge. 
5. Click Save. 
6. Navigate to the Prospect record then the Prospect Constituency tab. 
7. Click on the "Plans" sub-tab. 
8. Open the Plan. 
9. Click the "Opportunities" tab.
10. Select "Go to Opportunity". 
11. Click on "Associated Revenue" tab. 
12. Note that the revenue shows incorrectly and has multiplied the the original amount. (What was $1,000,000 is now $3,000,000) 

Environment

 Blackbaud CRM
 4.0
 4.0.180.16

Was this article helpful?