• Selecting Bump will insert a day pushing the rest of the schedule back one day
  • Selecting Skip will skip over the day, and the next day will take it’s place in the rotation

If a school meant to Bump and selected to Skip instead (or visa versa), the rest of the schedule will be off. To fix this, the school can edit the Master Schedule cycle and change the Day rotation.

To change the schedule cycle:

  • From the persona menu, select onRecord
  • Select “Schedule” under Procedures
  • Click Master Schedule and select the appropriate School Level
  • Click Options and select “Edit Cycle”
  • Make sure the date for which you want to change the rotation for is correct - if it isn't, click Change Date and select a new date
  • Select the Day for which you would like to reset the cycle to from the dropdown menu
  • Click Save & Exit