Note : Before you proceed with the following instructions, back up the database. If your organization integrates multiple Blackbaud products, refer to the Additional Requirements section of the backup article.


1. In Administration, select Globally change records

2. Highlight Financial and select New Change, opening a New Change window

3. On the General tab, within the Available fields column, expand Schedule, expand Schedule detail

4. Double click on Schedule date, opening new Schedule date Edit Change Parameters Window

5. Select the operation you would like to perform (ex. Replace 01/01/06 with 01/01/07) and select OK.

6. Select desired filters on Filters tab

7. Select Preview Changes, opening a new Preview Modifications window

8. Preview changes to be made, and select Change Now to change the generation schedule for the selected financial aid billing schedules