1. In Allocation Management, Pools, open the pool
2. In the Project ID grid, scroll to the bottom of the project list
3. Enter or select the Project ID
4. Save and close the pool
5. In Allocations, open the allocation using the updated pool
6. Select Allocation, Refresh from Pool from the menu bar
7. Save and close the allocation
8. Repeat steps 5, 6, and 7 for all allocations that use the updated pool