The error is occurring in a formula:

Convert the String field to a Date-Time format.

Original formula code: {PRIMARYGRADUATIONDATE.EN_US} < #07/07/09#

Updated formula code: Date({PRIMARYGRADUATIONDATE.EN_US}) < #07/07/09#

Please refer to Converting a String to a Date field (BB246110) for more information.



The error is occurring in the Select Expert:

Convert the Date-Time field to a Date format.

Original Select Expert code: {PROPOSALDATEEXPECTED.EN_US} is greater than or equal to 01/01/2013

Create a formula to convert the Proposal Date Expected Date-Time field to a Date field: Date({PROPOSALDATEEXPECTED.EN_US})
Then use the formula in the Select Expert instead of the Proposal Date Expected field.

Updated Select Expert code: {@ProposalDateConverted} is greater than or equal to 01/01/2013