1. In Records, click Budgets.
  2. Select Budget, Budget Tools from the menu bar.
  3. Select Copy/Forecast budget and click Next.
  4. Select the appropriate filters and click Next.
  5. In the Select a source scenario frame, select the budget scenario and fiscal year you want to copy. This will be the basis of the forecasted budget.
  6. In the Select a destination scenario frame, select the budget scenario and fiscal year to which you want to copy the source budget. This is the budget you are forecasting. 
  7. Select the periods you want to copy.
  8. Select Budget, Actuals, or Actuals+Encumbrance from the copy drop-down list.
  9. Select either Amount or Percent to copy, click Next.
  10. Verify the information is correct and click Copy/Forecast Now.
  11. Click OK once completed.