Revenue Update batch incorrectly updates default campaign based on adjustment date

When a campaign has a specific date range and associated designation, it will default onto new revenue records based on the designation and gift date.  When a revenue record is adjusted to a designation that has the same campaigns associated with it, the campaign on the revenue record should not change.  When the gift is adjusted manually from the payment record, the campaign remains the same.  However, when the gift is adjusted via a revenue update batch, the campaign changes to correspond to the adjustment date instead of the original revenue date.

Download and install the latest patch, which contains all fixes from previous patches. If you are running an older version, download and install the latest version and then the patch. 