BBDW Leap Year failure

The Blackbaud Data Warehouse ETL process is failing on February 29, 2012.  There is some date manipulation to update date ranges based on the current date and there is en error when figuring out information for February 29, 2013. 
The ETL will refresh successfully on March 1, 2012

or

If the process needs to be run today you should be able to disable the BBDW_DIM_DATE_CURRENTDATE package.
  1. Update the BBDW_PackageList.txt file in C:\Program Files\Microsoft SQL Server\100\DTS\Packages\BBETL\BBInfinity_RPT_BBDW
  2. Set the Enabled Value to 0 for the package
  3. We should see the following:
    "Enabled","Package"
    "1","BBDW_CONFIGINFO.dtsx"
    "1","BBDW_DELETEDIDS.dtsx"
    "1","BBDW_DIM_DATE.dtsx"
    "0","BBDW_DIM_DATE_CURRENTDATE.dtsx"
    "1","BBDW_DIM_SOURCE.dtsx"
    "1","BBDW_DIM_SITE.dtsx"
  4. The package will need to be re-enabled tomorrow.

Environment

 2.91

Was this article helpful?


Thanks for your feedback! Did this solve your issue?

Comments (optional):


Thanks for your feedback!
We're glad it was helpful but sorry it didn’t solve your issue. If you need assistance, click Chat with Support below.
We’re sorry to hear that. Please tell us why.

 I don't like how this works.

 The answer is confusing.

 The answer didn't match what I was searching for.

Additional Comments (optional):


Thanks for your feedback! If you need assistance, click Chat with Support below.
Thanks for your feedback. Help us make our products even better by sharing details in our Idea Banks or our online Community.
Thanks for letting us know. We'll work on clarifying the information in the article. If you need assistance, click Chat with Support below.
Thanks for letting us know. We'll work on updating the search engine to return more relevant results.