Pledge Reminder process is outputting the original pledge date in the NEXTINSALLMENTDATE field

Pledge Reminder process is outputting the original pledge date in the NEXTINSALLMENTDATE field.  This should be a reminder of the due date of the next installment.

The reason it is pulling back a null date is because the NEXTINSTALLMENT only pulls installments that are past due.

 

So, if the installment date is 8/1 and we run the process on 8/2 and the 8/1 installment has not yet been sent, then it will pull back the installment for 8/1. If we run the process again, it will not pull back any installments because it will see the 8/1 installment reminder has already been sent.

 

 

Environment

 3.0.516.42

Was this article helpful?


Thanks for your feedback! Did this solve your issue?

Comments (optional):


Thanks for your feedback!
We're glad it was helpful but sorry it didn’t solve your issue. If you need assistance, click Chat with Support below.
We’re sorry to hear that. Please tell us why.

 I don't like how this works.

 The answer is confusing.

 The answer didn't match what I was searching for.

Additional Comments (optional):


Thanks for your feedback! If you need assistance, click Chat with Support below.
Thanks for your feedback. Help us make our products even better by sharing details in our Idea Banks or our online Community.
Thanks for letting us know. We'll work on clarifying the information in the article. If you need assistance, click Chat with Support below.
Thanks for letting us know. We'll work on updating the search engine to return more relevant results.