Steps for plan outline are not inheriting the correct start date when adding plan outline

When adding a plan outline to a prospect plan, the start dates of the steps are based on today's current date and not the date on the plan outline. 
We're currently evaluating this issue for a fix in a future release 

Steps to Duplicate

1. Select Prospect> Configuration > Major giving setup.
2. Create a plan outline
3. Create an objective and enter a value for "days from start"- I used 2
4. Add a prospect plan to a prospect
5. Enter 7/1 for the plan start date
6. On the steps tab, select the plan outline
7. Notice the dates are going off of today's date and not the start date of the plan 

 

Environment

 Blackbaud CRM
 4.0
 4.0.141.0

Was this article helpful?


Thanks for your feedback! Did this solve your issue?

Comments (optional):


Thanks for your feedback!
We're glad it was helpful but sorry it didn’t solve your issue. If you need assistance, click Chat with Support below.
We’re sorry to hear that. Please tell us why.

 I don't like how this works.

 The answer is confusing.

 The answer didn't match what I was searching for.

Additional Comments (optional):


Thanks for your feedback! If you need assistance, click Chat with Support below.
Thanks for your feedback. Help us make our products even better by sharing details in our Idea Banks or our online Community.
Thanks for letting us know. We'll work on clarifying the information in the article. If you need assistance, click Chat with Support below.
Thanks for letting us know. We'll work on updating the search engine to return more relevant results.