Error: The UPDATE statement conflicted with the CHECK constraint 'CK_REVENUESCHEDULE_NEXTTRANSACTIONDATEVALID'. The conflict occurred in database 'database name', table 'dbo.REVENUESCHEDULE'.

When a editing a posted pledge it's possible to change the designation splits.  Sometimes when editing a pledge, after changing the designations an error message is given regarding the revenue revenue schedule on the pledge record.
We're currently evaluating this issue for a fix in a future patch or service pack.  

Steps to Duplicate

1. Open the pledge
2. Click the Designation hyperlink
3. Highlight a row and delete
4. Click Distribute evenly which will place the entire amount in one designation
5. Click Yes to the message regarding paid installments
6. Click Yes to the message regarding recognition
7. Click Edit installment designations to verify that all installments are showing the proper designation
8. Fill out the adjustment fields
9. Save the pledge -- the error occurs
 

Environment

 Blackbaud CRM
 3.0

Was this article helpful?


Thanks for your feedback! Did this solve your issue?

Comments (optional):


Thanks for your feedback!
We're glad it was helpful but sorry it didn’t solve your issue. If you need assistance, click Chat with Support below.
We’re sorry to hear that. Please tell us why.

 I don't like how this works.

 The answer is confusing.

 The answer didn't match what I was searching for.

Additional Comments (optional):


Thanks for your feedback! If you need assistance, click Chat with Support below.
Thanks for your feedback. Help us make our products even better by sharing details in our Idea Banks or our online Community.
Thanks for letting us know. We'll work on clarifying the information in the article. If you need assistance, click Chat with Support below.
Thanks for letting us know. We'll work on updating the search engine to return more relevant results.